Project: Fisheries Road Reconstruction

Project Duration: 12 April – 17 May 2021

Overview: Fisheries Road between Dempster Road & Hicks Road will be closed for the project duration.

The work will include changes to the existing pavement to remove clay based material and mitigate water leaching which is currently resulting in the road failure.

There is currently an average of 1400 daily movements on Fisheries Road, the nominated project duration is during a reduction of vehicle movements.

The work will include widening the road from 7.4m to 10m of seal, installation of culverts to divert the water and formation stabilization.

The work will be conducted by Shire of Esperance and Sub Contractors.

Detours will be in place, please see map for further information.

Updated: 26/02/2021