Works completed in the last fortnight:

  • Line marking completed to southern carpark.
  • Finishing of median strip, final trim & clean up to southern carpark area.
  • Exposed aggregate concrete paths to southern area installed.
  • All concrete tilt panels have now been manufactured.
  • Structural steel fabrication & painting ongoing – Columns, rafters, bracing and purlins on site.
  • Continuing installation of mains water and fire line along harbour road boundary.