Overall, works are proceeding well with the project on schedule. 

  • Roof sheeting completed to stadium area.
  • Purlins & Girts completed to the amenities building.
  • Wall sheeting commencing on the stadium
  • Brickwork commencing on amenities building – north end store area.
  • Aluminium door and window frames delivered to site ready for installation.
  • Hydraulic Contractor has completed the stormwater and fire main extension to the western andnorthern face of the existing stadium.
  • Prewire and comms cabling completed for Main Stadium area.