Roof sheeting is now complete and wall cladding has commenced. The project continues to progress within programme and budget.

  • Roof sheeting & insulation installed to stadium area – final 3 bays to complete.
  • Safety mesh installed to sports stadium walls.
  • Courts marked out to allow positioning of electrical & comms services
  • Electrical and comms cabling prelay continuing for stadium building.
  • Structural steel erection for the amenities building complete except for purlins and girts installed.
  • Stormwater & fire service installed to existing sports stadium running toward north eastern end.
  • Painting – seal coat to top of panels and around openings to prepare for wall sheeting & louvres.