The Esperance Indoor Sports Stadium Project is moving along with a significant amount of ground works being completed. The following has been achieved.

  • The Southern swale is well underway with some services being reinstated with new route/depth due to depth and position of swale. 
  • Clean fill has been transported to the site to achieve the footing levels needed for the sports stadium and amenities buildings. 
  • Surveying of gridlines and set out. 
  • Comprehensive compaction testing. 
  • Existing asbestos piping has been removed. 
  • Electrical conduits and cabling has been installed to the tennis court clubrooms. 
  • CPE specialists installed CT metering on the Site Main Switchboard. 
  • Installation of stormwater to eastern side of existing building