The Esperance Indoor Sports Stadium Project is moving along with a significant amount of ground works being completed. The following has been achieved.

  • Set out, excavation, compaction  and concreting of Pad footings for the Stadium were completed.
  • Clean fill imported and compacted to achieve under slab level for the sports stadium buildings.
  • Hydraulic contractor excavated & installed deep sewer line which extended from the Water Corporation junction in the south east corner of the site through to the amenities building.
  • Electrical contractors have completed the changeover of the new mains power to the tennis club. Now the power is sourced from the SMSB behind the Ports clubroom.
  • Structural steel shop drawings completed and currently reviewed by engineer.
  • Offsite works in the structural steel fabrication shop preparing stadium column components and cleats.

Read more about the project.