Works completed over the last fortnight:

  • Reticulation & electrical services relocated at southern swale for irrigation.
  • Reconnection of electrical feed to switchboard on Black Street.
  • Both electrical & hydraulic prelay completed to the buildings.
  • Concrete slabs for the main building – stadium, stores, foyer & amenities have been completed except one more pour for the wet area.
  • Hydraulic contractor has completed installation with all the major services - stormwater, water, fire, and sewer to the crossover at the Black Street entrance in preparation for the southern carpark.
  • Fabrication of structural steel work continuing off site with cross bracing and rafters for the Stadium being fabricated and painted.
  • Tilt Panel plan is completed with engineer approval.
  • Preparations for tilt panel manufacture has commenced on site.