The project is progressing well and is on schedule with the below works recently completed.

  • Final earthworks trim completed for stadium slab
  • Formwork completed for main stadium floor slab
  • Utility laying as prelay completed under main stadium floor slab
  • Concreted 1/8 of a section of the main stadium floor slab. Concreting will be completed in 8 stages
  • Continue with storm water, water, fire and sewer installation around the southern carpark
  • Fabrication works for the structural steel work are being progressed.
  • Tilt Panel shop drawing are being progressed