The project is progressing well and is on schedule with the below works recently completed.
- Final earthworks trim completed for stadium slab
- Formwork completed for main stadium floor slab
- Utility laying as prelay completed under main stadium floor slab
- Concreted 1/8 of a section of the main stadium floor slab. Concreting will be completed in 8 stages
- Continue with storm water, water, fire and sewer installation around the southern carpark
- Fabrication works for the structural steel work are being progressed.
- Tilt Panel shop drawing are being progressed