Works completed in the last fortnight:

  • Formwork is being completed for the stores areas ready for pouring this week.
  • Stadium concrete slab has been completed approx. 3500 m2.
  • 2 Fire Hydrant block walls completed.
  • Installation of electrical and communications conduit prelay in the amenities area has commenced.
  • Hydraulic contractor has completed all the major services - stormwater, water, fire, gas and sewer installation around southern carpark areas.
  • Fabrication of structural steel work continued off site with portals for the Stadium being fabricated ready for painting.
  • Tilt Panel plan is being prepared.
  • WorkSafe Notified for tilt panel manufacture proposed commencement 22 July 2019.