Landscaping work continues on the headland, as part of the Esperance Waterfront Project.

The hardwood timber edging for the walking paths has been installed on the northern side of the headland. On the southern side of the headland excavation is being completed to fill the walking paths.

Construction of the retaining walls that will support the jetty boardwalk, that lead from the Esplanade to the Tanker Jetty, has commenced. The boardwalk will follow the positioning of the first 80 metres of decayed jetty that was removed during the construction of the headland.

Work has also started on irrigation for the headland area, with a trench for reticulation systems being dug.